Cover photo: Malcolm Neal (CC BY-SA 2.0, cropped) · Source
UK Farm Renewable Energy — Last updated: October 2026 (see correction note below). This guide covers the four big farm-scale renewables (solar PV, wind, anaerobic digestion and biomass), the heat pump add-on, the grid-connection bottleneck that decides what you can actually build, the planning rules, and the SFI 2026 / Capital Grants 2026 funding picture as it stands in 2026. It is general information from a working salad and arable holding in Suffolk, not engineering, planning or tax advice. Cost figures are honest 2026 ranges and should be checked against live dealer quotes before any kit is ordered.
Correction, 13 October 2026: an earlier version of this guide got several facts wrong. It said rooftop solar on farm buildings was permitted development under Class A up to 1MW; it is Class J, and the 1MW cap was removed in December 2023. It gave the Green Gas Support Scheme Tier 1 tariff as 5.5-6.0p/kWh and attributed the scheme’s extension to the Autumn Statement 2024; the 2026/27 rates are 6.71p and 7.09p, the extension came through regulations in June 2024, and a 2026 amendment extends the commissioning deadline to 2030. It described a December 2024 Ofgem Connections Action Plan; the plan was published in November 2023 and the queue reform was approved in April 2025. It said a heat pump at 11.2p/kWh was competitive with oil at 60p a litre; oil at that price delivers heat at about 6.4p/kWh, so it was not, and oil prices have been updated to October 2026 levels. It also misstated Tesco’s 2032 Scope 3 target, described the 2018 energy-crop rule as a cap by mass (it was by biogas yield), gave the G98 limit as 11kW per phase (it is 16A, about 3.68kW, per phase), said SFI 2026 opened in spring (it opened on 30 June), and said a DNO budget estimate costs £300 (most are free). It also said wind turbines up to 11.1m on agricultural buildings were permitted development; that right applies only to domestic premises. Later the same day we also corrected the rooftop solar payback (7-10 years understated it; on this guide’s own figures it is nearer 4-7), the heat pump payback (8-15 years did not follow from the running costs), the description of onshore wind planning policy, the regional wind load factors and the mains gas price.
We had a conversation around the kitchen table in late February that I suspect a lot of farms have had this winter. The electricity standing charge on the packhouse bill had ticked up again. The day-rate had not come down to anything you could call cheap. The supermarket buyer had sent us a Scope 3 questionnaire wanting our carbon numbers per kilo of iceberg by the end of the contract year. And the south slope of the implement shed roof was sitting there in the rain catching nothing.
So I rang the land agent and told him I wanted to take another proper look at the renewables question. Solar PV first, because we are in Suffolk and the irradiance figures are as good as anywhere in the country. Then everything else. I have been around the block on this once before and walked away. Five years on the numbers are different, the grants are different, the supermarket buyer is asking different questions, and the grid connection queue is the elephant in every meeting room. This guide is what I have learned this winter, written down.
A way through this story
Why this is on the agenda again in 2026 — UK Farm Renewable Energy
Three things have changed at once. The first is that wholesale electricity prices, while off the 2022 spike, have settled at a level meaningfully above the pre-2021 average. Day-ahead baseload through 2025 traded mostly between £70 and £110 per MWh on the N2EX, which translates into a working-farm import price in the 22-32p/kWh range once standing charges, network costs and supplier margin are loaded on.[1] A salad packhouse with vacuum coolers, a wash line and a cold store is not a small consumer of that.
The second is the supermarket Scope 3 angle. The big four are now requiring grower-level emissions data and pushing for verified reductions on a year-on-year basis. Tesco is aiming for net zero across its value chain by 2050, with SBTi-validated targets to cut Scope 3 emissions from farming and land use by 39%, and its other Scope 3 emissions by 55%, by 2032 against a 2019/20 baseline; Sainsbury’s, Asda, Morrisons and the discounters are running similar programmes through Sedex and SBTi.[2] Generating your own electricity, displacing red diesel for heat, and getting a credible carbon line on a packhouse audit is no longer just nice to have. It is starting to show up in tender scoring. The measurement side of that is in our UK carbon farming and net zero guide.
The third is diversification income. With BPS gone, SFI 2024 paused mid-stream, and SFI 2026 reopened on a tighter footing, the on-farm income mix matters more than it did. Renewables are one of the few diversification streams where the long-term contract structure is reasonably visible, the supermarket gatekeeping doesn’t apply, and the planning regime, in 2026 at least, is moving in the right direction rather than the wrong one. Whether the maths actually clears for a given farm is the question this guide is trying to answer honestly.
Solar PV: the one most farms should look at first
Solar is the least-bad starting point for almost any holding, and on a south-facing roof with a meaningful daytime electrical load it usually pays. The two big decisions are rooftop versus ground-mount, and self-consumption versus export.
Rooftop solar on existing agricultural and packhouse buildings is permitted development under Class J of Part 14 of the General Permitted Development Order. Since 21 December 2023 there has been no capacity limit; the old 1MW cap was removed. The conditions that remain are physical. Panels on a pitched roof can’t stand more than 0.2m proud of the slope, kit on a flat roof can’t rise more than a metre above it, and the right doesn’t apply on a listed building or a scheduled monument. Planning has stopped being the constraint on a big shed roof. The DNO connection is now the constraint, and we come to that below. For commercial-scale rooftop in 2026, installers’ published price guides put commercial rooftop at roughly £700 to £1,100 per kWp, falling with system size, and higher for smaller installs where the fixed costs of design, scaffolding and DNO paperwork weigh more heavily. There is no current official benchmark, so get at least three quotes.[3] That is for the panels, inverters, mounting, AC and DC cabling, switchgear and commissioning. It does not include battery storage, which is a separate decision.
Ground-mount on agricultural land sits in different territory. A field-scale array of 1-5MW typically lands at £600-800/kWp installed, with the lower end achieved on simple ground, no piling, no high-voltage step-up. Above 5MW you are in solar farm developer territory and the deal structure moves to long-term lease payments rather than self-build. Field rents for commercial solar leases are commonly quoted at around £850 to £1,100 per acre per year, usually index-linked, on terms of 30 to 40 years or more. Offers vary with grid access, size and location, so take independent agent and legal advice.[4] That is meaningfully more than arable rent and it is contracted income, but you give up the field for the duration and the BPR position needs careful thought (see the inheritance tax interaction below).
The export question is where most growers waste energy. The Smart Export Guarantee, which replaced the Feed-in Tariff for new installations from January 2020, requires every electricity supplier with more than 150,000 customers to offer at least one tariff for exported renewable electricity. The tariff floor is set at “above zero”, which is not a useful floor. The actual SEG tariffs in spring 2026 sit in a wide band from around 3p/kWh on the worst supplier offerings to 15p/kWh and occasionally higher on time-of-use products from Octopus, Good Energy and one or two others.[5] Above 5MW, or where the export economics matter more, a Power Purchase Agreement (PPA) with a third party offers a fixed or floor-and-share price for a 5-15 year term. The trap is signing a PPA at a 2023 forward curve when 2026 wholesale is sitting higher.
The arithmetic that matters is self-consumption. Every kilowatt-hour you generate and use yourself displaces a 25-30p import unit. Every kilowatt-hour you export earns 5-10p on a typical SEG tariff. The gap is the entire economic case for solar on a working farm with a daytime load. A packhouse running coolers, fans and conveyors through a summer day from seven in the morning to seven at night will self-consume 60-80% of a properly-sized rooftop array. A grain store with a few weeks of dryer load and not much else will self-consume 15-25%. Size the array to the load, not the roof.
Battery storage changes the maths once self-consumption above 80% is on the table. BloombergNEF’s December 2025 survey put average stationary-storage battery pack prices at US$70/kWh, but the pack is only part of an installed system. Installed commercial systems in the UK cost several times that per kWh, so get quotes.[6] Payback on storage on its own is hard to make. Stacking storage with a solar array, peak-shaving the day-rate import on no-sun days and (where the DNO will allow) trading on a flexibility market starts to get the simple payback into single digits in a working year. Most farms aren’t there yet. By 2027 or 2028 they probably are.
If I’m honest, the elephant in the rooftop discussion is the grid connection. We will come to it.
Wind: where it still works, and that is not many places
Wind on farms had a moment between roughly 2008 and 2015 when the Feed-in Tariff carried a working economic case for sub-50kW machines, and a separate moment for medium-scale up to 500kW under the Renewables Obligation. Both subsidy regimes are closed to new entrants. The Contract for Difference allocation rounds favour developments at scale that no working farm bids into.
Small-scale wind under 50kW and medium-scale up to 500kW now stand on Smart Export Guarantee revenue and self-consumption only, the same as solar. Installed cost is much higher per kW than solar. The last government cost study (2015, at 2014 prices) put turbines of 15-50kW at about £3,200 per kW and 100-500kW at about £2,300 per kW, before inflation, which on the maths needs a high-quality wind site to clear. Get current quotes.[7] The site matters more than the region. DESNZ puts the average onshore wind load factor in 2025 at 24.1% in both England and Scotland, and 26.0% in Wales, but individual sites sit well either side of that. Without a measured wind speed for your own site, any payback figure is guesswork.
Planning is the bigger problem. The 2015 changes to footnote 49 of the National Planning Policy Framework, which required onshore wind sites to be in areas identified as suitable in the local plan and to have demonstrable community support, killed the small-scale on-farm market in England. In July 2024 the government removed those two tests, so onshore wind applications in England are now judged in the same way as other energy development.[8] Scotland and Wales never had the English tests, which is part of why most of the UK’s onshore wind sits outside England: Scotland alone produced 64% of UK onshore wind generation in 2025.
Wake effects on neighbouring crops are a side issue most farms underweight. A 50m turbine creates a wake zone running 8-12 rotor diameters downwind in which wind speed and turbulence vary. For arable crops the agronomic impact is real but small. For polytunnel and glasshouse sites, the structural loading from gusts and the shading need a proper assessment, not a back-of-envelope.
What I’d actually do on wind in 2026, on a Suffolk salad and arable holding, is nothing. The site is wrong, the planning regime is hard, and the capital required pays back faster on solar with batteries. If you sit on top of a hill in Caithness, the answer is different.
Anaerobic digestion: real economics at scale, not at every farm
Anaerobic digestion sits in a different category from solar and wind. It is not principally an electricity story. It is a gas story, a digestate-as-fertiliser story, and a feedstock-management story, and it works at scale or it does not work at all.
A farm-scale AD plant in 2026 typically lands in the 250kWe to 1MWe band for combined heat and power generation, or in the 250-500 m³/hr biomethane production band for grid injection. The last government cost study put farm AD with CHP at roughly £4,500 to £6,000 per kWe (2015, at 2014 prices, with a wide range either side). Biomethane-to-grid plants cost more once the upgrading and injection kit is included, and there is no reliable published per-unit figure, so budget from a feasibility study.[9] On top of that, feedstock storage, digestate handling, gas cleaning and grid injection or grid connection costs typically add 20-40% to the headline build figure.
The income side has changed. The Renewable Heat Incentive, which was the backbone of biomethane economics through 2014-2021, closed to new entrants on 31 March 2021.[10] Its replacement, the Green Gas Support Scheme, supports biomethane injection into the grid through a 15-year tariff structured in three tiers based on annual output. Regulations that took effect in June 2024 extended the scheme so that new stage 1 applications can be made until 31 March 2028. A further amendment, the Green Gas Support Scheme (Amendment) Regulations 2026, gives plants until 31 March 2030 to commission, with a shorter tariff life for those that commission late. For 2026/27, Ofgem’s tariff table puts Tier 1 (the first 60,000MWh a year) at 7.09p/kWh for plants whose tariff started on or after 1 October 2024, and 6.71p/kWh for older starts. Tiers 2 and 3 pay progressively less. Tariffs rise with CPI each April.[11] That tariff, in combination with the wholesale gas price, is what makes a biomethane plant work. A CHP plant relies on the SEG export plus self-consumed heat, which is a much harder case to clear at farm scale.
The feedstock decision is the one that actually makes or breaks an AD project. Maize silage at scale, grown on contract within 25 miles of the plant, was the standard build through the 2010s. The 2018 RHI reforms limited support for crop-fed plants: new biogas and biomethane plants had to get at least half their biogas yield from wastes or residues to have all their output supported, and the public discomfort with food crops being burned for power has pushed most newer plants towards food waste, slurry and crop residues.[12] Slurry-only AD on a livestock farm is technically straightforward and financially marginal: the gas yield per tonne of slurry is low. Food-waste AD is technically harder (depackaging, contamination, pasteurisation requirements) and financially better, with gate fees from local authorities and food processors paying you to take the feedstock. Most working farm-scale AD now operates on a mix.
The digestate is genuinely valuable. PAS 110-compliant whole digestate, separated into liquor and fibre, gives you a nitrogen-rich liquid fertiliser and a soil-conditioner solid that displaces a meaningful chunk of bagged fertiliser.[13] On our holding the application has been to neighbouring arable contractors rather than our own field veg blocks (food safety protocols on leafy salad rule it out for those rotations), but for the right farm the displaced fertiliser cost adds £80-150/ha to the case.
If I’m honest, AD at sub-250kWe is mostly broken economics. AD at 500kWe to 1MWe with a credible feedstock contract and a reasonable grid injection deal is a real business with real returns, but it is a £3-8 million project and a 15-20 year commitment. Any farm thinking about an AD plant should walk through the numbers with the Anaerobic Digestion and Bioresources Association and a specialist consultant before any meaningful spend on design.
Biomass: where heat is the answer, not electricity
Biomass on farms in 2026 is essentially a heat story, and it survives because some heat loads on farms are big, year-round and currently met by oil or LPG. Kerosene was trading at around 113-119p a litre in mid-October 2026, which works out at about 11p per kWh of fuel before boiler losses.
The Renewable Heat Incentive, which made the working economic case for farm biomass boilers through the 2010s, closed to new non-domestic applications in March 2021.[10] There is no direct replacement scheme for biomass heat. What remains is the underlying displacement: a 100-200kW biomass boiler running on wood chip displaces oil at around 11p per kWh of fuel at autumn 2026 prices and replaces it with wood chip, which is usually much cheaper per kWh, though the price depends on moisture content and delivery distance (and less again if you are making your own).[14] On a heat load that runs through the year, a 150kW boiler with its fuel store and plant room is a six-figure investment, and the simple payback without subsidy depends on your heat load and the chip price you can secure. Get quotes for both before committing.
The Biomass Suppliers List is the regulatory backbone. Any commercial biomass user buying chip or pellet wants the supplier to be BSL-listed, both for the carbon and sustainability credentials and (historically) for RHI compliance.[15] Self-supply from on-farm woodland is allowed under separate self-supply registration rules.
Chip versus pellet is the perennial decision. Chip is cheaper per delivered kWh, takes more storage volume, requires bigger fuel-handling kit (augers, walking floors), and lives or dies on moisture content (M30 chip burning hot, M50 chip choking the boiler). Pellet is more expensive, more compact, more forgiving in handling, and works for smaller loads and tighter sites. A working farm with a barn worth of chip storage and a 100kW+ heat load almost always goes chip. A horticultural office or domestic-scale heat load goes pellet.
Where biomass actually pays, and where I’d point a working farmer first, is heated glass and polytunnel sites with year-round propagation, big cold-store sites with a meaningful heat demand for offices and pack areas, and any farm with an existing oil-fired heat load over 100kW. The numbers do not work for replacing a small farmhouse boiler with biomass; for that load an air-source heat pump is now the better call.
Looking back, I’d say biomass on farms is a more boring proposition than it was in the RHI years and a more honest one. The economics now stand on the displaced fuel cost, which is real, rather than a tariff that may or may not still be there in eight years.
Heat pumps: the smaller-scale option most farms are now asking about
Air-source heat pumps for farm office, dwelling and small-scale process loads have moved from niche to mainstream over the last three years. Ground-source remains an option where the geology and the available land work, but the CapEx differential is large and the payback on the extra cost rarely justifies it on a farm site.
The median air-source heat pump installation under the Boiler Upgrade Scheme cost about £12,500 in 2024/25. A larger farmhouse and office, or one needing radiator and cylinder upgrades, will cost more, so get quotes.[16] The Boiler Upgrade Scheme gives £7,500 towards an air-source heat pump replacing a fossil-fuel system in England and Wales, and until March 2027 an extra £1,500 where the property is heated by oil or LPG and has no mains gas connection.[17] The headline coefficient of performance for a well-installed modern unit on a properly insulated property is 3.0-3.5; the seasonal performance factor on a rural off-grid property with mediocre insulation is more often 2.2-2.8, which still beats oil at most market prices but does not produce the cost saving the marketing suggests.
The COP reality is the bit that catches farmers off guard. A heat pump that runs at SCOP 2.5 with electricity at 28p/kWh delivers heat at 11.2p/kWh. Kerosene holds about 10.35kWh a litre, so through a 90%-efficient boiler, oil at 60p a litre delivers heat at about 6.4p/kWh and oil at 115p at about 12.3p. That swing decides the comparison. With oil cheap, a mediocre heat pump loses to it outright. At mid-October 2026 prices it roughly breaks even, and a well-installed unit at SCOP 3.0 or better (about 9.3p/kWh at 28p electricity) wins. Against mains gas, at about 8p/kWh under the October 2026 price cap (nearer 9p per kWh of heat through a boiler), it usually still loses, though by less than it used to. On a Suffolk farm off the gas grid, replacing oil, the maths now usually clears, as long as you aren’t betting on oil staying this high. On a farm on the gas grid, it usually does not.
The grid connection problem: the elephant in every room
Anybody designing a new renewables project on a UK farm in 2026 needs to start with the Distribution Network Operator queue. Connection waits in much of the country are now multi-year. The government and Ofgem published a Connections Action Plan in November 2023. In April 2025 Ofgem approved the National Energy System Operator’s reform package (known as TMO4+), which replaces first-come, first-served with a queue that puts projects that are ready to build, and that the system needs, at the front. The pipeline it had to sort was more than 700GW of projects against a network that doesn’t have the headroom.[18] In some regions, particularly East Anglia, Yorkshire and the Scottish Borders, new export connection offers above 1MW have been quoted dates in 2030, 2032 and beyond.
What this means in practice for a farm. A small array of up to 16A per phase (about 3.68kW on a single-phase supply, or about 11kW across three phases) usually connects under G98, where you notify the DNO after installation. Anything larger goes through G99, which needs the DNO’s approval before you connect. Above 50kW the queue starts to bite, and above 1MW it bites hard. A small-to-medium rooftop install (50-200kW) on most farms in 2026 will get a connection offer within months. A field-scale ground-mount above 1MW will not.
Two practical workarounds matter. The first is “export-limited” or “zero-export” installs, which contractually cap your export at a defined level (often zero) and avoid the queue for export capacity. For a self-consumption-led project this is fine; for an export-led project it kills the case. The second is the queue reform itself. The re-ordering NESO and the network companies have been working through since 2025 pushes speculative or stalled projects out of the way. It has freed up some capacity, but the headline waits are still long.
The honest advice is: get the DNO budget estimate before you spend money on design. Most DNOs provide one free, usually within 10 to 20 working days, and it gives you a non-binding figure that tells you whether the project is two years out, five years out, or ten years out. Anybody designing a large array without that conversation is designing to a queue that may not have them.
Planning: the rules that decide what you can put up
Most farm renewables sit within permitted development rights or low-friction prior approval routes, but it depends on scale.
Solar on existing agricultural buildings is permitted development in England under Class J of Part 14 of the GPDO 2015, with no capacity limit since December 2023. It is subject to the physical limits on how far panels stand off the roof, and it doesn’t apply to listed buildings or scheduled monuments.[19] Ground-mount arrays beyond the small stand-alone allowance under Class K (no more than 9m² of panel) need full planning. Wind is different. Part 14 only gives permitted development rights for wind turbines on domestic premises: one microgeneration turbine on a detached house, or a single stand-alone turbine up to 11.1m to the blade tip within a house’s curtilage, built to MCS standards. There is no equivalent right for turbines on farm buildings or farmland, so a farm turbine needs full planning. AD plants, biomass installations of meaningful scale, and any associated grid infrastructure all need full planning.
Most farm building works that go alongside renewables (extensions to grain stores to fit a battery room, new switch rooms, internal modifications) sit within the Class A and Class B Part 6 agricultural rights covered in our Class Q & R permitted development guide. The key change in the 21 May 2024 amendments was the lift of the Class A ground-area limit from 1,000m² to 1,500m², which makes a serious renewables-supporting building project achievable without full planning.
Funding: SFI 2026, Capital Grants 2026, SEG and GGSS
The funding picture for farm renewables in 2026 is messier than it was in the RHI era and slightly cleaner than it was during the 2024 SFI pause. There are four streams worth knowing about.
The Sustainable Farming Incentive 2026 opened in two windows: the first on 30 June 2026 for small farms and farms without an existing agreement, the second on 22 September 2026, when applications quickly exceeded the £233 million budget. It runs on a tighter footing than the 2024 scheme, with a smaller per-action menu and a reset payment structure.[20] No SFI 2026 action pays directly for installing renewable generation, but several actions interact with renewables decisions: hedgerow and biodiversity actions are compatible with ground-mount solar where the developer agrees a biodiversity plan, and nutrient management actions interact with AD digestate use. The action menu and rates are covered in our SFI 2026 actions and payment rates guide.
Capital Grants 2026 opened at the end of July 2026 with a £225 million budget, and Defra reported 75% of it allocated by 1 August. The items are aimed at water quality, hedgerows, biodiversity and land management rather than energy, so check the item list for anything that touches a renewables project; the fuller scope is in our UK Farming Grants Guide.
The Smart Export Guarantee remains the headline export revenue mechanism for solar, wind and AD plants below 5MW. It is not a grant; it is a regulated obligation on suppliers to offer a tariff for exported renewable electricity. The tariff is the supplier’s commercial offering; shop it.[5]
The Green Gas Support Scheme is the live tariff for biomethane injection. New stage 1 applications close on 31 March 2028 and the scheme runs to a capped budget. Any farm seriously looking at GGSS-supported biomethane should be in the queue well before that, not up against the deadline.[11]
How energy revenue interacts with diversification and inheritance tax
This is the bit a working farm should think hardest about, and the bit most rural surveyors miss in the renewables sales pitch.
A standalone solar array generating electricity for export and self-consumption sits at the trading end of the spectrum on most readings. A long-term solar lease to a developer, by contrast, looks much more like an investment activity and risks being treated as such for Business Property Relief purposes. The leading authorities on the trading-versus-investment distinction (Pawson, Vigne) have not been tested on solar leases at appellate level, but the Treasury’s December 2025 reforms to APR/BPR, capping combined relief at £2.5 million per individual at the 100% rate above April 2026, raise the stakes on the question.[21] Our Farm Inheritance Tax 2026 Guide walks through the interaction in detail.
The diversification framing matters too. A renewables income stream sits inside the wider diversification mix on most working farms, alongside Class R commercial conversions, Class Q residential conversions, on-farm retail and rural enterprise. The interaction of those streams with the farming business as a whole is the subject of our Farm Diversification 2026 working farmer guide — which is currently being drafted in parallel with this piece, so the cross-link will go live when both are published.
Where I land on this: a working farm running a self-consumption-led rooftop solar array with a packhouse load and a small SEG export does not have a BPR problem. A working farm signing a 35-year ground lease for a 50MW solar farm has a BPR question and needs to take advice before the contracts are signed.
Honest comparison: payback and £/MWh by technology
The rough numbers, for a working farm in eastern England in spring 2026, look like this on the back of an envelope.
Rooftop solar 100-500kW, self-consumption-led: simple payback of roughly 4-7 years. That assumes £700-950/kWp installed, about 1,050kWh a year from each kWp in Suffolk, 60-70% of the output used on site at 20-25p a unit, the rest exported at 5p, and maintenance at 1.5% of the cost a year. Lifetime levelised cost is around £60-85/MWh and the IRR is in the teens or better on a typical packhouse load. Export most of it instead (a grain store using a fifth of its output) and payback stretches towards 12 years.
Ground-mount solar at 1-5MW: simple payback of 8-12 years self-built, lifetime LCoE of £45-65/MWh, IRR 6-10% pre-storage. Lease-to-developer: contracted income of £800-1,200/acre/year, no upfront capital, but the BPR question is live.
Small wind under 50kW on a typical lowland English site: simple payback of 12-18 years on current SEG tariffs, marginal at best. Don’t bother unless your site has a measured wind speed above 6 m/s.
Medium wind 250-500kW on a high-quality upland site: simple payback of 8-12 years, viable but planning-constrained.
Farm-scale AD 500kW-1MW with a credible feedstock and GGSS tariff: simple payback of 8-12 years on a £4-8m build, IRR 8-14% on the right feedstock contract, very dependent on the gate-fee economics.
Biomass heat 150-300kW replacing oil on a year-round heat load: simple payback of 6-10 years, no subsidy needed.
Air-source heat pump on a farmhouse off the gas grid: the payback depends almost entirely on the oil price. At mid-October 2026 prices, heat from oil costs about 12p/kWh and heat from a heat pump at SCOP 2.5-3.0 about 9-11p, so the running-cost saving is modest and the payback on the extra cost over a new oil boiler is long, even after the £7,500 BUS grant. At 60p oil it doesn’t pay back on running costs at all. The case is strongest when the oil boiler is due for replacement anyway.
What working farms typically get wrong
The first mistake is over-sizing. A solar array sized to the roof rather than the load exports most of its production at SEG rates that don’t pay it back. Size to the load, leave roof space for a future expansion, and add the second array when the load grows.
The second is ignoring the grid wait. Designing a 2MW ground-mount in a region with a 2032 connection date means the financial model is ten years out before the engineer arrives.
The third is signing 25-year PPAs at the wrong price. PPA prices struck in 2022-2023 against inflated forward curves are running below current market in 2026 and growers are stuck. A short PPA (5-7 years) with a re-pricing clause beats a long one at a low strike.
The fourth is forgetting the insurance and maintenance line. Solar and wind kit need O&M budgets of around 1-2% of CapEx per year. AD plants need 3-5%. Biomass boilers need annual cleaning and ash handling that is a real labour line, not zero.
The fifth, and the most common, is buying off a salesman rather than off a feasibility study. The salesman is selling a system. The feasibility study is figuring out whether you should buy one.
Tim’s view: what makes sense for a salad and arable holding in Suffolk
Suffolk is a high-irradiance area for the UK. The EU’s PVGIS solar database puts mean annual horizontal irradiation in coastal Suffolk at about 1,130 kWh/m² (2005-2020 average, ranging from about 1,075 to 1,200 year to year), which is among the better numbers anywhere in Britain.[22] On a working salad and packhouse holding with a daytime load running from cooler season through summer harvest, rooftop solar is almost a no-brainer. The numbers on our south-facing implement shed roof, on the figures we have walked through this winter, give a simple payback inside nine years before any battery uplift, and that is at conservative assumptions.
AD I would not touch at our scale. The feedstock economics on a 250kWe plant don’t work, and we don’t have the tonnage of suitable feedstock to justify a 500kWe or larger plant on our own holding. The right structure for a farm our size, if AD is the answer, is a contributing-feedstock supplier into a neighbour’s larger plant, not a standalone build.
Wind is off the table. Lowland Suffolk capacity factors of 20-22% don’t carry the case. Planning is no longer the brick wall it was before July 2024, but that doesn’t fix the economics.
Biomass is a maybe, and only because we still run an oil-fired propagation glass on one block and the chip economics, on a five-year fuel curve, look interesting. The capital cost on the boiler and the chip handling needs running through properly before any kit is ordered.
Heat pumps will go into the farmhouse and the office at the next boiler-end-of-life, with the BUS grant. That is a domestic decision, not a farm-business decision, but it is the right decision.
Where I’d point most working salad and small arable holdings first, in 2026, is rooftop solar on every south-facing roof you can run a feasibility study on, sized to the load, with a battery upgrade penciled in for year three or four. Do that before you do anything else. Then read the SFI 2026 menu and the Capital Grants 2026 list with the renewables decision in mind, because the soil and water actions are easier to layer on once the energy strategy is in place. Then, and only then, ask the wind, AD and biomass questions.
The kitchen-table version is shorter. The grid-connection people are the bottleneck, the salesman is not the consultant, the supermarket buyer is going to keep asking, and the south slope of the implement shed roof is sitting there in the rain catching nothing. That last bit, at least, is fixable.
Sources
[1] Ofgem, Wholesale market indicators, ofgem.gov.uk; Department for Energy Security and Net Zero, Quarterly Energy Prices December 2025, gov.uk: https://www.gov.uk/government/statistics/quarterly-energy-prices-december-2025
[2] Tesco PLC, Sustainability Report 2026: tescoplc.com; Sainsbury’s, Plan for Better, about.sainsburys.co.uk; Science Based Targets initiative, Companies taking action, sciencebasedtargets.org.
[3] Installer price guides, for example Spirit Energy, Commercial solar cost, payback and ROI (2026): spiritenergy.co.uk; for the last official UK cost study, DECC, Small-scale Generation Cost Update (2015): gov.uk.
[4] Stephens Scown, Solar farms: benefits for landlords (2023): stephens-scown.co.uk; Strutt & Parker, Solar farm offers need careful thought: struttandparker.com.
[5] Ofgem, Smart Export Guarantee, ofgem.gov.uk: https://www.ofgem.gov.uk/environmental-and-social-schemes/smart-export-guarantee-seg
[6] BloombergNEF, Lithium-ion battery pack prices (2025 survey): about.bnef.com.
[7] DECC, Small-scale Generation Cost Update (2015): gov.uk; DESNZ, Regional renewable electricity in 2025 (load factors): gov.uk.
[8] Ministry of Housing, Communities and Local Government, National Planning Policy Framework, December 2024, gov.uk; Policy statement on onshore wind, 8 July 2024, gov.uk: https://www.gov.uk/government/publications/policy-statement-on-onshore-wind; DESNZ, Regional renewable electricity in 2025, gov.uk.
[9] DECC, Small-scale Generation Cost Update (2015), section 2.5.4 on anaerobic digestion: gov.uk.
[10] Ofgem, Renewable Heat Incentive: closure, ofgem.gov.uk.
[11] Ofgem, Green Gas Support Scheme tariff table 2026 to 2027, ofgem.gov.uk: https://www.ofgem.gov.uk/publications/green-gas-support-scheme-tariff-table; DESNZ, Green Gas Support Scheme (GGSS): open to applications, gov.uk: https://www.gov.uk/government/publications/green-gas-support-scheme-ggss; The Green Gas Support Scheme (Amendment) Regulations 2026 (SI 2026/1051).
[12] The Renewable Heat Incentive Scheme Regulations 2018 (SI 2018/611), regulation 74: legislation.gov.uk; for electricity, the Feed-in Tariffs (Amendment) Order 2017 (SI 2017/131): legislation.gov.uk.
[13] BSI, PAS 110:2014 Specification for whole digestate, separated liquor and separated fibre derived from the anaerobic digestion of source-segregated biodegradable materials (sponsored by WRAP): wrap.ngo.
[14] Kerosene prices from Fueltool and BoilerJuice national averages, 13 October 2026; HETAS, Biomass installation register, hetas.co.uk.
[15] Department for Energy Security and Net Zero, Biomass Suppliers List, biomass-suppliers-list.service.gov.uk.
[16] DESNZ, Boiler Upgrade Scheme 2026-2030: summary business case (median installation cost from Boiler Upgrade Scheme statistics): data.parliament.uk.
[17] Department for Energy Security and Net Zero, Boiler Upgrade Scheme, gov.uk: https://www.gov.uk/apply-boiler-upgrade-scheme
[18] DESNZ and Ofgem, Connections Action Plan, November 2023, gov.uk; Ofgem, Decision on connections reform (TMO4+), April 2025, ofgem.gov.uk; National Energy System Operator, Connections reform technical decision, neso.energy.
[19] Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 14, legislation.gov.uk.
[20] Defra, Sustainable Farming Incentive 2026: scheme handbook, gov.uk; Defra Farming blog, SFI26: Window 1 now open (30 June 2026) and SFI26: Window 2 now open (22 September 2026), defrafarming.blog.gov.uk; Rural Payments Agency, SFI 2026 actions and payment rates, gov.uk.
[21] HM Treasury, Autumn Budget 2024; HMRC, Reforms to agricultural property relief and business property relief, gov.uk; HMRC v Pawson [2013] UKUT 050 (TCC); HMRC v PRs of Vigne [2018] UKUT 357 (TCC).
[22] European Commission Joint Research Centre, PVGIS monthly radiation data (52.2°N, 1.5°E), queried 18 November 2026: re.jrc.ec.europa.eu.
About the author
Tim Harfield runs a salad and vegetable holding in Suffolk and has done for 21 years, with two recent seasons of arable layered into the rotation. The packhouse is on site and the electricity bill is the line item that has stared back hardest from the Q4 management accounts each of the last three winters. The renewables question is one we have walked around twice before and are walking around again, and this guide is what came out of doing the work properly this time.
The headline: rooftop solar pays on most working farms with a daytime load and a south-facing roof, and the place to start. AD only stacks at scale and only with a credible feedstock contract. Wind is off the table for most of lowland England in 2026. Biomass earns its keep on year-round heat loads. And the grid-connection conversation comes before the engineer’s drawings, not after. BritFarmers is independent, takes no commission, and is written by working farmers for working farmers.
You’ve reached the end of this story.




